Follow along as we move through the project design and building process over the next couple of years.
-
Educate. Innovate. Succeed.
The Dassel-Cokato School Board called for a special election on Tuesday, August 9, 2022, to authorize general obligation bonds not to exceed $17,900,000 for facility improvements. The voters within Dassel-Cokato School District #466 approved the single-question request. The unofficial results are: 1,300 Yes (56.2%) and 1,000 No (43.48%)."Thank you for your support. We are excited to move forward with projects that will update our facilities and offer new opportunities to our students, staff and community."
- Mark Raymond, Superintendent
Weekly Updates: 2024 Summer Construction Projects
-
Weekly Update: Ending 8/2/2024
Ongoing/Completed Tasks for the Week Ending 8/2/2024:
▪ Area B flooring 90% complete
▪ Area C Flooring 75% complete
▪ Area K sheetrock complete
▪ Back area concrete is completeExterior shop concrete pads:
MS FACS lab:
-
Weekly Update: Ending 7/19/2024
Ongoing/ Completed Tasks for the Week Ending 7/19/2024:
▪ Area B above ceilings complete.
▪ Area K sheetrock 95% complete
▪ Area C painting complete
▪ Cokato ES electrical rough in complete
▪ Dassel demo complete, walls getting prepped for paint next week.FACS Room lights:
Bathroom Time:
-
Weekly Update: Ending 7/12/2024
Ongoing/ Completed Tasks for the Week Ending 7/12/2024:
▪ Area K Admin office framing complete
▪ Area K rough in complete
▪ Area B Painting complete
▪ Area C painting 90% complete
▪ Area H MS woodshop Masonry walls complete
▪ Sped Room Sheetrock 50% complete
▪ Cokato ES MEP demo complete and walls starting to be framed.High School Conference Room Wall:
High School Bathroom Walls:
-
Weekly Update: Ending 7/3/2024
Ongoing/ Completed Tasks for the Week Ending July 3rd:
▪ Area K Admin office framing 95% complete
▪ Area K rough in ongoing.
▪ Area B Painting has started first coat applied.
▪ Area C mud and tape has started.
▪ Front entry canopy steel has been installed.
▪ Area H MS woodshop Masonry wall going up.
▪ Area H RTU Set today.
▪ Cokato ES MEP demo complete and walls starting to be framed.High School Offices:
High School Shop Cement Work:
-
Weekly Update: Ending 6/21/2024
Ongoing/ Completed Tasks for the Week Ending June 21st:
▪ Area K Admin office Demo 95% complete
▪ Area B Inspections completed.
▪ Area C rough in and walls in progress.
▪ Front entry canopy footings complete.
▪ Area H MS woodshop footing complete.
▪ Area H roof steel and curb installed.
▪ All AHUs are now on-site in the rec center.
▪ Dassel ES abatement is complete and ready for us to continue.
▪ Cokato ES MEP demo is complete and ceilings will start coming out next week.Wall Infills:
Office Area Demolition:
-
Weekly Update: Ending 6/14/2024
Ongoing/Completed Tasks for the Week Ending June 14th
▪ Demo in area C complete.
▪ Demo on woodshop and metals shop walls complete.
▪ Area B underground plumbing complete and floor poured.
▪ Area K Admin office needed Abatement.
▪ Area H MS woodshop demo is complete.
▪ Area I MS FACS lab lighting complete.
▪ Dassel ES ready for abatement
▪ Cokato ES diffusers are demoed and electrical will be next week.New Walls:
Office Area Demolition:
-
Weekly Update: Ending 6/7/2024
Ongoing/ Completed Tasks for the Week Ending June 7th
▪ Demo in area B completed.
▪ Demo on woodshop walls in progress.
▪ Area B underground plumbing in progress, state inspection next week.
▪ Area K Admin office Demo will be completed next week.
▪ Area H MS woodshop demo is in progress.
▪ Area I MS FACS lab demo is in progress.
▪ Dassel ES demo to be completed on Monday for Abatement contractor.Woodshop Demolition:
Bathroom Demolition:
-
Weekly Update: Ending 5/30/2024
Ongoing/ Completed Tasks for the Week Ending May 30th
▪ Brick is almost complete on exterior shop addition.
▪ Demo is ongoing in Area B, C, K, and I
▪ Floor Protection in installed throughout school area.Floor Protection:
Brick Work:
-
Weekly Update: Ending 5/10/2024
Ongoing/ Completed Tasks for the Week Ending May 10th.
▪ Footings are complete.
▪ Foundation CMU walls are complete.
▪ Backfill and compaction is complete.
▪ Interior and Exterior CMU walls are ongoing.
▪ Tie-in for Metals shop will be ongoing for the next few days.Foundation Walls
New Addition Backfill:
CURRENT BUILDING 466 UPDATES
Project Schedules
-
Project Scopes Overview 2023
High School/ Middle School Projects
- Replacement of 1971 windows
- New hot water boiler heating
- Changing piping to convert steam-heated areas to hot water
- Replacing air handling units in the shop, science, family and consumer science, and agricultural areas
- Disconnecting from the old well and connecting to city water
- Replacing four air handlers serving the gym and mezzanine
-
Project Scopes Overview of 2024
High School / Middle School Projects
- Replacing Heating, Ventilation, and Air Conditioning systems in High School Office
- Build a new addition to expand the Woods, Welding, and Machine Shops
- Build an addition for Small Engine space
- Renovate and expand the family and consumer science, and agriculture classrooms
- Renovate the science suites to support programming needs, including a robotics lab
- Redesign the High School entrance to provide a secure entry and a welcoming entry plaza
- Renovate the Middle School Industrial Tech lab
- Renovate and expand the Middle School Family and Consumer Sciences area
- Remodel space to support DCD programming along with an accessible restroom
- Outdoor project yard
- Renovate selected outdated ganged restrooms
Elementary School Projects
- Pilot project(s) within Cokato Elementary
- Pilot project(s) within Dassel Elementary